Sec. 7.

(a) The following governmental entities are excluded from payment of the fees in subsection (b):

(1) County, municipality, or township that is defined as a unit under IC 36-1-2-23.

(2) A nonprofit organization.

(3) A conservancy district.

(4) A school corporation.

(5) A regional water or sewage district.

(b) The following fees for a public water supply construction application must be remitted at the time a permit application is

submitted to the department:

TYPE PROCESSING FEE
New public water supply treatment plant:
Ground water:
Up to 500,000 gallons per day $875
Greater than 500,000 gallons per day $1,750
Surface water:
Up to 500,000 gallons per day $1,250
Greater than 500,000 gallons per day $2,500
Public water supply treatment plant expansion:
Up to fifty percent (50%) design capacity:
Greater than 500,000 gallons per day $1,250
Up to 500,000 gallons per day $625
Greater than fifty percent (50%) design capacity:
Greater than 500,000 gallons per day $2,500
Up to 500,000 gallons per day $1,250
Other water treatment facilities:
Wells $860
Pump or pump station $175
Chemical addition $430
Storage tank $345
Miscellaneous process modification $100 per process
All water distribution system:
2,501 - 5,000 linear feet $260
5,001 - 10,000 linear feet $430
Greater than 10,000 linear feet $860

(c) The fee is not refundable after staff review and processing of the permit application has commenced.

(d) For public water systems, the department shall bill for annual operation fees as follows:

(1) For a community water system with more than four hundred (400) service connections, the annual operation fee is ninety-five cents ($0.95) per service connection.

(2) For a community water system with four hundred (400) or fewer service connections, the annual operation fee is three hundred fifty dollars ($350).

(3) For a nontransient noncommunity water system, the annual operation fees are as follows:

Number Served Fee
25 - 100 $150
101 - 250 $180
251 - 500 $240
501 - 1,000 $300
1,001 - 3,300 $450
3,301 - 5,000 $600
5,001 - 10,000 $1,500
more than 10,000 $3,000

(4) For a transient noncommunity water system, the annual operation fees are as follows:

Type of Transient Noncommunity Water System Fee
Groundwater $100
Purchase $50
Surface $200

Disclaimer: These regulations may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.