Authority: IC 13-14-8; IC 13-14-9; IC 13-15-2; IC 13-18-1; IC
13-18-3; IC 13-18-4; IC 13-18-16-8
Sec. 4.
(a) A
responsible person who elects to participate in the General Construction Permit
Program shall submit a NOI that complies with this section and is received by
the commissioner at least thirty (30) calendar days before the commencement of
construction of the proposed water main.
(b) A NOI must be submitted on forms obtained
from the commissioner or a computer generated reproduction that is similar in
appearance and identical in content to the forms generated by the
commissioner.
(c) The NOI must be
submitted by certified mail to the address provided on the NOI form.
(d) The NOI must include the following:
(1) The names, firms, addresses, and
telephone numbers of the following:
(A) The
responsible person.
(B) The
responsible person's professional engineer.
(C) The responsible person's developer,
resident project representative, or person who by other means is representing
the construction aspects of the proposed project.
(2) The title of the proposed project for
which the NOI is submitted.
(3) The
name of the public water system and the corresponding public water system
identification number, mailing address, and telephone number.
(4) The county and nearest public
intersection and the nearest quarter section in which the construction project
is located or, if the section, township, and range are not available, the
latitude and longitude of the approximate center of the construction project to
the nearest fifteen (15) seconds.
(5) A statement from the responsible person
that indicates which one (1) of the following two (2) methods of construction
activity notification the responsible person will comply with:
(A) The proposed construction schedule is
included with the NOI.
(B) The
proposed construction schedule will be submitted separate from the NOI at least
ten (10) working days before the commencement of the construction and will
include a copy of the information required in subdivisions (1) through
(4).
(6) The
certifications required in section 7 of this rule.
(7) A dated signature from the public water
system certifying that the public water system will fulfill the requirements of
section 12 of this rule.
(8) The
average daily customer demand and the peaking factor of the proposed water
main.
(9) The public water
system's:
(A) daily capacity; and
(B) two (2) year average peak.
(10) Any fees as required by
327 IAC 8-3-7.
(11) A copy of any approvals from the
commissioner of alternative technical standards that will apply to the proposed
water main.
(12) A copy of any
approvals from the commissioner of alternate average daily customer demand,
peaking factor, or peak daily customer demand that will apply to the proposed
water main.
(13) A copy of any
written authorization of a duly authorized representative of a responsible
person.