Indiana Administrative Code
Title 327 - WATER POLLUTION CONTROL DIVISION
Article 8 - PUBLIC WATER SUPPLY
Rule 3.1 - Permitting Authority of Units for Water Main Extension Construction
Section 3.1-2 - Permitting authority and responsibilities
Current through September 18, 2024
Authority: IC 13-14-8; IC 13-14-9; IC 13-15-1-2; IC 13-15-2-1; IC 13-18-3-1; IC 13-18-3-12; IC 13-18-4-1
Affected: IC 13-11-2; IC 13-13-5-1; IC 13-18-2
Sec. 2.
(a) The plans for a water main extension are not required to be submitted to any state agency for a permit, permission, or review, unless required by the federal law, if the following are met:
(b) The proposed construction of a water main must be in accordance with the following:
(c) The other requirements specified in rules that have been adopted by the board and must be adhered to in the permitting of a public water main include the following:
(d) Units shall notify the commissioner of all public water main construction permits that the unit has issued by submitting to the department, on the effective date of the permit, a copy of each issued permit. Each submission must contain the following information for each issued permit:
(e) The commissioner may approve alternatives to the notification procedure described in subsection (d) if requested. The alternative notification procedure must provide equivalent information to that required under subsection (d) to be considered for approval.
*Copies of these publications may be obtained from the Government Publishing Office, www.gpo.gov, or are available for review at the Indiana Department of Environmental Management, Office of Legal Counsel, Indiana Government Center North, 100 North Senate Avenue, Thirteenth Floor, Indianapolis, Indiana 46204.