Indiana Administrative Code
Title 327 - WATER POLLUTION CONTROL DIVISION
Article 6.1 - LAND APPLICATION OF BIOSOLID, INDUSTRIAL WASTE PRODUCT, AND POLLUTANT-BEARING WATER
Rule 3 - Land Application; General Requirements
Section 3-4 - Permit duration and transition requirements
Current through September 18, 2024
Authority: IC 13-14-8-7; IC 13-15-1-2; IC 13-15-2-1; IC 13-18-3-1; IC 13-18-12-4
Affected: IC 13-15-3
Sec. 4.
(a) Except as specifically provided for elsewhere in this article or Indiana statute, permits may be issued by the commissioner for any period of time not to exceed five (5) years as specified by IC 13-15-3.
(b) A permit application for the land application of biosolid, industrial waste product, or pollutant-bearing water submitted after the effective date of this article must comply with applicable sections of this article.
(c) If a person holding a valid permit under this article has made a timely and complete application for a renewal, the existing permit does not expire until a final determination on the application is made by the commissioner. The commissioner may seek injunctive relief with regard to the continuing activity of the permit applicant while the permit application is pending if the continuing activity of the permit applicant constitutes a threat to the environment or the public health, safety, or welfare.
(d) Any permits granted under this article will continue to be in effect under the rules effective at the time the permit was issued until the permit is renewed as required.