Indiana Administrative Code
Title 327 - WATER POLLUTION CONTROL DIVISION
Article 5 - INDUSTRIAL WASTEWATER PRETREATMENT PROGRAMS AND NPDES
Rule 17 - Definitions; Pretreatment Rules
Section 17-24 - "Significant noncompliance" defined
Current through September 18, 2024
Authority: IC 13-14-8; IC 13-15-1-2; IC 13-15-2-1; IC 13-18-2; IC 13-18-3
Affected: IC 13-11-2; IC 13-13-5-1; IC 13-18-4
Sec. 24.
"Significant noncompliance" means the status of an industrial user that has caused or allowed a violation that meets one (1) or more of the following criteria:
(1) Chronic violations of wastewater discharge limits, defined as those in which sixty-six percent (66%) or more of all of the measurements taken during a six (6) month period exceed, by any magnitude, a numeric pretreatment standard or requirement, including instantaneous limits, as defined by 40 CFR 403.3(l).
(2) Technical review criteria (TRC) violations, defined as those in which thirty-three percent (33%) or more of all of the measurements for each pollutant parameter taken during a six (6) month period equal or exceed the product of the numeric pretreatment standard or requirement, including instantaneous limits, as defined by 40 CFR 403.3(l), multiplied by the applicable TRC (TRC equals one and four-tenths (1.4) for biochemical oxygen demand, total suspended solids, fats, oil, and grease and one and two-tenths (1.2) for all other pollutants except pH).
(3) Any other violation of a pretreatment standard or requirement as defined by 40 CFR 403.3(l), such as daily maximum, long-term average, instantaneous limit, or narrative standard that the POTW determines has caused, alone or in combination with other discharges, interference or pass through, including endangering the health of POTW personnel or the general public.
(4) Any discharge of a pollutant that has:
(5) Failure to meet, within ninety (90) days after the schedule date, a compliance schedule milestone contained in a local control mechanism or enforcement order for:
(6) Failure to provide, within forty-five (45) days after the due date, required reports, such as the following:
(7) Failure to accurately report noncompliance.
(8) Any other violation or group of violations, which may include a violation of BMPs, that the POTW determines will adversely affect the operation or implementation of the approved POTW pretreatment program.