Indiana Administrative Code
Title 327 - WATER POLLUTION CONTROL DIVISION
Article 5 - INDUSTRIAL WASTEWATER PRETREATMENT PROGRAMS AND NPDES
Rule 17 - Definitions; Pretreatment Rules
Section 17-13 - "New source" defined
Current through September 18, 2024
Authority: IC 13-14-8; IC 13-15-1-2; IC 13-15-2-1; IC 13-18-2; IC 13-18-3
Affected: IC 13-11-2; IC 13-13-5-1; IC 13-18-4
Sec. 13.
(a) "New source" means any building, structure, facility, or installation that is discharging or may discharge pollutants, and its construction commenced after the publication of proposed pretreatment standards under Section 307(c) of the Clean Water Act ( 33 U.S.C. 1317(c)) that will be applicable to the source, if those standards are thereafter promulgated in accordance with Section 307(c) of the Clean Water Act, provided one (1) of the following conditions is met:
(b) Construction on a site at which an existing source is located results in a modification rather than a new source if the construction does not create a new building, structure, facility, or installation meeting the criteria of subsection (a)(2) or (a)(3) but otherwise alters, replaces, or adds to existing process or production equipment.
(c) Construction of a new source as defined in this section has commenced if the owner or operator has:
Options to purchase, contracts that can be terminated or modified without substantial loss, and contracts for feasibility, engineering, and design studies do not constitute a contractual obligation under this section.