Section 13.1-7 - Total enclosure monitoring requirements
Current through March 20, 2024
Authority: IC 13-14-8; IC 13-17-3-4; IC 13-17-3-11
Affected: IC 13-15; IC 13-17
Sec. 7.
(a) In addition to the requirements in section 1(d) of this rule, and the requirements in section 6 of this rule, the owner or operator of a secondary lead smelter using a total enclosure shall do the following:
(b) Within one hundred eighty (180) days after written approval of the continuous monitoring system plan by the department, the owner or operator of a secondary lead smelter shall install and operate a continuous monitoring system that consists of the following:
(c) The owner or operator of a secondary lead smelter shall calibrate each digital differential pressure monitoring system in accordance with the manufacturer's specifications at least once every twelve (12) calendar months or more frequently if recommended by the manufacturer.
(d) The owner or operator of a secondary lead smelter shall obtain prior written approval from the department for any changes to the location or operation of the continuous monitoring system.
(e) The owner or operator of a secondary lead smelter shall initiate corrective actions within thirty (30) minutes of a monitoring system alarm.
(f) The owner or operator of a secondary lead smelter shall notify the department within seven (7) days of any physical changes to the total enclosure including, but not limited to, ventilation capacity and building size.
(g) The owner or operator of a secondary lead smelter shall maintain the following on site for a period of three (3) years and have available the following records for an additional two (2) years: