Sec. 2.
(a) This rule applies to the issuance of a registration, permit, modification approval, or operating permit revision required under this article and the sources or emissions unit or units required to obtain a registration, permit, modification approval, or operating permit revision under this article, except where rules in this article establish more specific requirements. No person shall construct, operate, or modify a source or emissions unit required to obtain a registration, permit, modification approval, or operating permit revision prior to issuance of a registration, permit, modification approval, or operating permit revision, except as provided in this article.
(b) Specific registration, permitting, modification approval, and operating permit revision requirements are located in the following provisions of this article:
(c) The commissioner may require the owner or operator of a source or emissions unit (excluding single-family dwellings) that has the potential to emit any air pollutant to complete a permit application. If after review of a permit application, the commissioner determines that the source or emissions unit is subject to the registration, permit, modification approval, or permit revision provisions under this article and is required to receive such registration, permit, modification approval, or permit revision, the commissioner may require the owner or operator of the source or emissions unit to obtain a construction or operating permit, modification approval, or permit revision prior to constructing, operating, or modifying the source or emissions unit.
(d) The requirement for a registration, permit, modification approval, or permit revision shall be based on the following:
(e) Any exemption granted under this rule shall apply only to the requirement to have prior approval before construction, operation, or modification of a source or emissions unit. An exemption under this rule does not exempt a source from any other requirements applicable to the source under this title.