Sec. 3.
(a) An applicant for a grant must provide project proposal assurances as set forth in this section.
(b) A project assurance must include the following:
(1) A
definition of abbreviated terms used in the provision assurances.
(2) Assurances that the acquisition,
development, and maintenance of projects will be performed under lawful
departmental standards. These assurances must set forth:
(A) accommodation for handicapped persons as
otherwise provided by law;
(B)
conformance with state bidding and contract requirements, including a
nondiscrimination clause;
(C)
project processing;
(D) record
maintenance, including a financial management system;
(E) terms for maintenance of a site after the
completion of a project; and
(F) a
demonstration the project is compatible with existing site conditions,
including sewers and utility facilities.
Disclaimer: These regulations may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.