Sec. 55.

Each application shall contain a description of each road, conveyor, or rail system to be constructed, used, or maintained within the proposed permit area. The description shall include a map, appropriate cross sections, and the following:

(1) Specifications for each culvert, bridge, drainage ditch, and drainage structure.

(2) A description of measures to be taken to comply with 312 IAC 25-6-65.

(3) Each plan shall contain a general description of each road, conveyor, or rail system to be constructed, used, or maintained within the proposed permit area.

Disclaimer: These regulations may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.