Indiana Administrative Code
Title 312 - NATURAL RESOURCES COMMISSION
Article 25 - COAL MINING AND RECLAMATION OPERATIONS
Rule 4 - Permitting Procedures
Section 4-49 - Surface mining permit applications; reclamation and operations plan; reclamation plan for siltation structures, impoundments, dams, and embankments, and refuse piles
Current through March 20, 2024
Authority: IC 14-34-2-1
Affected: IC 14-34
Sec. 49.
(a) Each application shall include a general plan and a detailed design plan for each proposed siltation structure, water impoundment, and coal processing waste dam, embankment, or refuse pile within the proposed permit area. The information required shall be provided as follows:
(b) Siltation structures, whether temporary or permanent, shall be designed in compliance with the requirements of 312 IAC 25-6-17. Any siltation structure or earthen structure that will remain on the proposed permit area as a permanent water impoundment shall also be designed to comply with the requirements of 312 IAC 25-6-20.
(c) Permanent and temporary impoundments shall be designed to comply with the requirements of 312 IAC 25-6-20 and the requirements of the Mine Safety and Health Administration at 30 CFR 77.216-1 and 30 CFR 77.216-2.
(d) Refuse piles shall be designed to comply with 312 IAC 25-6-36 through 312 IAC 25-6-39.
(e) Coal processing waste dams and embankments shall be designed to comply with the requirements of 312 IAC 25-6-34, 312 IAC 25-6-36, and 312 IAC 25-6-43 through 312 IAC 25-6-45. Each plan shall also comply with the requirements of the Mine Safety and Health Administration, 30 CFR 77.216-1 and 30 CFR 77.216-2, and shall contain the results of a geotechnical investigation of the proposed dam or embankment foundation area to determine the structural competence of the foundation that will support the proposed dam or embankment structure and the impounded material. The geotechnical investigation shall be planned and supervised by an engineer or engineering geologist according to the following:
(f) If the structure meets the Class B or C criteria for dams in TR-60 or meets the size and other criteria of 30 CFR 77.216(a), each plan under subsections (b), (c), and (e) shall include the following:
(g) If the proposed siltation structure, water impoundment, coal processing waste dam, or embankment is permanent and the: