Sec. 35.
(a) Within ten (10) years after the completion date of the main extension, a utility shall not permit a subsequent connector to connect to a main extension until after the subsequent connector has paid the required subsequent connector's fee to the utility.
(b) Applicants for service connections for lots in subdivision and tract developments which are included in the original depositor's main extension agreement, are not required to pay a subsequent connector's fee, unless otherwise specifically provided for in the main extension agreement.
(c) If a prospective customer with frontage land that was unplatted on one (1) or both sides of the street at the time the main extension was installed later subdivides this frontage prior to the expiration of the ten (10) years after the completion date of the main extension in such a manner that some or all lots will not require service directly from that main extension, the customer is considered to have requested a lateral extension from that main extension to serve the customer's land. The utility, in that case, shall collect from the prospective customer prior to installing the requested lateral main extension, a subsequent connector's fee for each equivalent lot of the frontage land used in determining the main extension cost per lot and which will not be served directly by the original main extension.