Indiana Administrative Code
Title 170 - INDIANA UTILITY REGULATORY COMMISSION
Article 5 - GAS UTILITIES
Rule 1 - Standards of Service
Section 1-9 - Periodic testing of meters

Universal Citation: 170 IN Admin Code 1-9

Current through September 18, 2024

Authority: IC 8-1-1-3; IC 8-1-2-4

Affected: IC 8-1-2

Sec. 9.

A public utility may not allow a gas meter to remain in service for longer than sixteen (16) years without either:

(1) checking it for accuracy and readjusting it if found to be incorrect beyond the limits established under section 8 of this rule; or

(2) verifying by statistical quality control sampling as established in the approved statistical quality control program in the fifteenth year in service, and in each succeeding year the meter is allowed to remain in service that the meter in the population sampled does not exceed an average accuracy figure of one hundred two percent (102%) or two percent (2%) above absolute accuracy of one hundred percent (100%) when tested at the meter's check and open rates with an acceptable quality level (AQL) equal to ten (10.0).

Disclaimer: These regulations may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.