Indiana Administrative Code
Title 170 - INDIANA UTILITY REGULATORY COMMISSION
Article 4 - ELECTRIC UTILITIES
Rule 9 - Vegetation Management Standards
Section 9-9 - Dispute resolution process during vegetation management
Current through September 18, 2024
Authority: IC 8-1-1-3; IC 8-1-2-4; IC 8-1.5-3-8
Affected: IC 8-1-2
Sec. 9.
(a) Upon request of the customer, the utility shall temporarily stay vegetation management on the customer's premises during the vegetation management only if one (1) of the following occurs or is disputed:
(b) At least one (1) member of the work crew must have the authority from the utility to discuss and attempt to resolve customer objections and must respond to the customer's inquiry or complaint. If the work crew cannot resolve the customer's objection regarding vegetation management, at least one (1) additional authorized utility representative must attempt to resolve the objection. If the utility is unsuccessful in resolving the objection, the utility shall provide to the customer the information required in 170 IAC 16-1-4(c)(5).
(c) A utility may proceed with the vegetation management where: