Sec. 3.
(a) This rule does not modify property rights. Utilities must have or obtain the following legal authority and must provide documentation in accordance with subsection (b):
(1) easements;
(2) rights of way;
(3) statutory authority;
(4) other legal authority; or
(5) the express or implied consent of the
property owner or customer; prior to trimming vegetation. The utility's ability
to secure a prescriptive easement may be presented to the customer to obtain
consent, but is not independent legal authority.
(b) Upon request by the customer within five (5) business days of the customer's receipt of the notice required under section 4 of this rule, the utility will provide one (1) of the following prior to vegetation management:
(1) A copy of the
easement or public right of way document that gives the utility the legal right
to enter the customer's property to perform vegetation management.
(2) If an easement or public right of way
document is not reasonably available, a copy of the authority that gives the
utility the legal right to enter the customer's property to perform vegetation
management.
Disclaimer: These regulations may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.