Indiana Administrative Code
Title 170 - INDIANA UTILITY REGULATORY COMMISSION
Article 4 - ELECTRIC UTILITIES
Rule 6 - Ratemaking Treatment of Qualified Pollution Control Property Under Construction
Section 6-5 - Approval modification
Current through September 18, 2024
Authority: IC 8-1-2-6.6
Affected: IC 8-1-8.5; IC 8-1-8.7; IC 8-1-27
Sec. 5.
After a utility has received the commission's approval for the use of qualified pollution control property in the utility's coal burning generating facilities as provided in sections 3 and 4 of this rule, the utility shall seek the commission's approval for the modified use of the qualified pollution control property where:
(1) the utility has added to the value of its property the value of the qualified pollution control property under construction for ratemaking purposes as provided in this rule; and
(2) the utility reasonably anticipates that it will use less Indiana coal as the primary fuel in its facilities after the qualified pollution control property becomes fully operational than the utility had anticipated when the commission approved the use of qualified pollution control property in the facilities.