Indiana Administrative Code
Title 170 - INDIANA UTILITY REGULATORY COMMISSION
Article 4 - ELECTRIC UTILITIES
Rule 6 - Ratemaking Treatment of Qualified Pollution Control Property Under Construction
Section 6-3 - Deemed approved

Universal Citation: 170 IN Admin Code 6-3

Current through March 20, 2024

Authority: IC 8-1-2-6.6

Affected: IC 8-1-8.5; IC 8-1-8.7; IC 8-1-27

Sec. 3.

The use of qualified pollution control property by a utility at one (1) or more of its electric generating facilities shall be deemed approved by the commission if:

(1) the utility has a valid certificate of public convenience and necessity authorizing the utility to use clean coal technology at the facilities under IC 8-1-8.7;

(2) the utility has a valid certificate of public convenience and necessity to construct, purchase, or lease a facility that will incorporate one (1) or more air pollution control devices under IC 8-1-8.5; or

(3) the utility's proposed use of qualified pollution control property is part of the utility's environmental compliance plan for which the utility has received and continues to possess commission approval under IC 8-1-27.

Disclaimer: These regulations may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.