Sec. 11.

The commission shall grant ratemaking treatment to qualified pollution control property under construction eligible for ratemaking treatment under IC 8-1-2-6.6, as provided in section 10 of this rule, on petition by a utility under IC 8-1-2-61 or at the request of a utility in any of the following:

(1) A proceeding involving the utility's base rates and charges or an adjustment to its rates, charges, or rate structures, except for a fuel cost adjustment proceeding under IC 8-1-2-42(d).

(2) A review proceeding under IC 8-1-8.5 or IC 8-1-8.7. The commission may grant ratemaking treatment under this section only for construction of qualified pollution control property associated with the generating facility or clean coal technology project under review.

(3) A review proceeding under IC 8-1-27.

Disclaimer: These regulations may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.