Indiana Administrative Code
Title 170 - INDIANA UTILITY REGULATORY COMMISSION
Article 4 - ELECTRIC UTILITIES
Rule 4.1 - Cogeneration and Alternate Energy Production Facilities
Section 4.1-7 - Interconnections; metering; costs
Current through September 18, 2024
Authority: IC 8-1-1; IC 8-1-2; IC 8-1-2.4
Affected: IC 8-1-2; IC 8-1-2.4
Sec. 7.
(a) The qualifying facility shall:
Breakers and/or switches capable of isolating the qualifying facility from the electric utility shall at all times be immediately accessible to the electric utility. The electric utility may isolate any qualifying facility at its own discretion if the electric utility believes continued parallel operation with the qualifying facility creates or contributes to a system emergency. System emergencies causing discontinuance of parallel operation are subject to verification by the commission. The facilities installed by the qualifying facility shall comply with 170 IAC 4-1-26(a) and the electric utility's rules and regulations for electric service in effect from time to time. The qualifying facility shall comply with the applicable requirements of 170 IAC 4-4.3.
(b) To properly record the number of kilowatt hours being purchased or sold by the electric utility or qualifying facility, the following configurations shall be the basis for metering:
(3) When the qualifying facility will simultaneously sell to and purchase from the electric utility, two (2) monodirectional meters shall be placed in a series arrangement between the electric utility's system and the qualifying facility, and a single, monodirectional meter shall be placed between the electric utility's system and the on-site load of the qualifying facility that will be served by the electric utility, as shown as follows:
(4) The metering equipment installed by the electric utility may be designed to recognize the different rate periods.
(5) The electric utility and the qualifying facility may agree to other metering arrangements.
(6) The electric utility may, solely at its option, install additional metering equipment at its own expense.