Indiana Administrative Code
Title 170 - INDIANA UTILITY REGULATORY COMMISSION
Article 4 - ELECTRIC UTILITIES
Rule 11 - Certification Requirements for the Construction, Purchase, or Lease of Small Modular Nuclear Reactors by a Public Utility
Section 11-4 - Definitions
Current through September 18, 2024
Authority: IC 8-1-1-3; IC 8-1-8.5-12.1
Affected: IC 8-1-1.1; IC 8-1-8.5; IC 8-1-8.8; IC 13-11-2-102; IC 13-11-2-216
Sec. 4.
(a) The definitions in IC 8-1-8.5-12.1 and this section apply throughout this rule.
(b) "Commission" means the Indiana utility regulatory commission.
(c) "CPCN" means a certificate of public convenience and necessity, as required under IC 8-1-8.5-2.
(d) "High level radioactive waste" has the meaning set forth in IC 13-11-2-102.
(e) "NRC" means the United States Nuclear Regulatory Commission.
(f) "OUCC" means the office of utility consumer counselor established under IC 8-1-1.1.
(g) "Public utility" has the meaning set forth in IC 8-1-8.5-1(a).
(h) "SMR" means a small modular nuclear reactor as defined in IC 8-1-8.5-12.1(a).
(i) "Spent nuclear fuel" has the meaning set forth in IC 13-11-2-216.