Indiana Administrative Code
Title 170 - INDIANA UTILITY REGULATORY COMMISSION
Article 4 - ELECTRIC UTILITIES
Rule 10 - Cost Securitization for Retired Electric Utility Assets
Section 10-4 - Definitions
Universal Citation: 170 IN Admin Code 10-4
Current through September 18, 2024
Authority: IC 8-1-1-3; IC 8-1-40.5-19
Affected: IC 8-1-1.1; IC 8-1-40.5
Sec. 4.
(a) The definitions in IC 8-1-40.5 and this section apply throughout this rule.
(b) "Case-in-chief" means the evidence and documentation provided by the utility in support of its petition, including those listed in section 5(c) of this rule.
(c) "Commission" means the Indiana utility regulatory commission.
(d) "OUCC" means the Indiana office of utility consumer counselor established under IC 8-1-1.1.
(e) "Removal costs" means those costs:
(1) incurred, or expected to be incurred, to physically remove retired utility generation facilities; and
(2) that have not already been recovered from customers.
(f) "Restoration costs" means those costs found to be just and reasonable by the commission, which:
(1) have not been recovered from customers; and
(2) are incurred, or expected to be incurred, to restore the site of retired utility generation facilities to a reasonable state as determined by applicable law.
Disclaimer: These regulations may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.