Indiana Administrative Code
Title 170 - INDIANA UTILITY REGULATORY COMMISSION
Article 4 - ELECTRIC UTILITIES
Rule 1.5 - Service to New Buildings
Section 1.5-2 - Master metering of new multi-unit structures
Authority: IC 8-1-2-69
Affected: IC 8-1-2-69
Sec. 2.
General Prohibition of Master Metering of New Multi Unit Buildings and Exceptions. All electricity delivered to a new building at which units of such premises are separately rented, leased or owned, shall be sold by the electric utility on the basis of individual meter measurement for each such occupancy unit, except for electricity used in hotels, motels and other similar transient lodging, or where the service applicant establishes in writing furnished to the utility before commencement of construction of the new building that costs of purchasing and installing separate meters in such building exceed the long run benefits of individual metering of units and would not substantially serve to meet any of the three objectives of the Act.