In the event that the recipient or a contractor is delayed, hindered in, or prevented from the performance of any act required by the contract by reason of any of the following:

a) strikes, lockouts, labor troubles;

b) unduly harsh weather conditions, not including foreseeable and ordinary adverse weather conditions such as rain and snow, which prevent the normal performance of the rehabilitation project;

c) inability to procure materials;

d) failure of power;

e) riots, insurrection, or war; or,

f) any Act of God;

the time of performance of such delayed party may be extended for a time period equal to such delay.

Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.