a) Upon a minimum 24-hour notice, the recipient shall allow the Department to inspect all books and records of the recipient relating to the project or task receiving funds under the contract. The recipient shall maintain the following until the expiration of three years after the project completion:
b) The recipient shall maintain a set of accounting records separately identifiable for the project funded by the State.
c) Subcontracts:
The recipient shall include the substance of the provisions of subsection (a) of this Section in all subcontracts entered pursuant to the contract.
d) Overpayment by State:
If the Department's final audit determines that the recipient's allowable costs are less than the amount that has been paid to recipient, that amount will be subtracted from the retained amount provided for in Section 800.380. An allowable cost is a line item, identified on the contract, for which the State has agreed to provide funds. If the retained amount is insufficient for these purposes, the recipient shall repay the Department within ninety days after the Department notifies recipient of the amount of said overpayment. The recipient reserves the right to correct its billing within ninety days after the Department notifies recipient of an overpayment by submitting other allowable costs for reimbursement. The recipient shall repay the State within ninety days after receiving Department notification of adjusted overpayment.