Illinois Administrative Code
Title 83 - PUBLIC UTILITIES
Part 467 - ELECTRIC INTERCONNECTION OF LARGE DISTRIBUTED ENERGY RESOURCES FACILITIES
Section 467.45 - Pre-Application Report
Current through Register Vol. 48, No. 38, September 20, 2024
a) In addition to the information described in Section 467.60, which may be provided in response to an informal request, a potential applicant may submit a formal written request form along with a non-refundable fee of $300 for a pre-application report on a proposed project at a specific site. The EDC shall provide the pre-application data described in this Section to the potential applicant within 20 business days after receipt of the completed request form and payment of the $300 fee. The pre-application report produced by the EDC is non-binding and does not confer any rights; the potential applicant must successfully file an application before it can interconnect with the EDC's system. The written pre-application report request form shall include the following information to clearly and sufficiently identify the location of the proposed point of interconnection:
b) Using the information provided in the pre-application report request form described in subsection (a), the EDC shall identify the substation/area bus, bank or circuit likely to serve the proposed point of interconnection. This selection by the EDC does not necessarily indicate, after application of the relevant review process, that this would be the circuit to which the project ultimately connects. The potential applicant must request additional pre-application reports if information about multiple points of interconnection is requested. Subject to subsection (c), the pre-application report shall include the following information:
c) The pre-application report need only include existing data. A pre-application report request does not obligate the EDC to conduct a study or other analysis of the proposed generator in the event that data is not readily available. If the EDC cannot complete all or some of a pre-application report due to lack of available data, the EDC shall provide the interconnection customer with a pre-application report that includes the data that is available. The provision of information on "available capacity" within the pre-application report represents the best information available to the EDC at the time of the reporting and does not imply that an interconnection up to this level may be completed without impacts.