Illinois Administrative Code
Title 83 - PUBLIC UTILITIES
Part 467 - ELECTRIC INTERCONNECTION OF LARGE DISTRIBUTED ENERGY RESOURCES FACILITIES
Appendix A - Certificate of Completion
Certificate of Completion
(To be completed and returned to the EDC when installation is complete
and final electric inspector approval has been obtained[1])
Interconnection Customer Information
Name: ____________________________________________________
Mailing Address: ____________________________________________
City: ____________________ State: _________ Zip Code: __________
Telephone (Primary): ________________ (Alternate): _______________
Facsimile Number: _______________ E-Mail Address: ______________
InstallerCheck if owner-installed
Name: ____________________________________________________
Mailing Address: ____________________________________________
City: __________________ State: ___________ Zip Code: __________
Telephone (Primary): ________________ (Alternate): _______________
Facsimile Number: ________________ E-Mail Address: _____________
Final Electric Inspection and Interconnection Customer Signature
The distributed generation facility is complete and has been approved by the local electric inspector having jurisdiction. A signed copy of the electric inspector's form indicating final approval is attached. The interconnection customer acknowledges that it shall not operate the distributed generation facility until receipt of the final acceptance and approval by the EDC as provided below.
Signed: _________________________ Date: _______________________
(Signature of interconnection customer)
Printed Name: _________________________
Check if copy of signed electric inspection form is attached
Check if copy of as-built documents is attached
................................................................................................................................
Acceptance and Final Approval for Interconnection (for EDC use only)
The interconnection agreement is approved and the distributed generation facility is approved for interconnected operation upon the signing and return of this Certificate of Completion by EDC:
Electric Distribution Company waives Witness Test?? (Initial) YesNo
If not waived, date of successful Witness
Test:____________________________ Passed: (Initial) ______
EDC Signature: __________________________________ Date: ________
Printed Name: ___________________________________ Title: __________
[1] Prior to interconnected operation, the interconnection customer is required to complete this form and return it to the EDC. Use contact information provided on the EDC's web page for generator interconnection to obtain mailing address/fax number/e-mail address.