Illinois Administrative Code
Title 83 - PUBLIC UTILITIES
Part 467 - ELECTRIC INTERCONNECTION OF LARGE DISTRIBUTED ENERGY RESOURCES FACILITIES
- Section 467.10 - Scope
- Section 467.20 - Definitions and Incorporations by Reference
- Section 467.30 - Waiver
- Section 467.40 - Technical Standards
- Section 467.45 - Pre-Application Report
- Section 467.50 - Interconnection Request Review
- Section 467.60 - General Requirements
- Section 467.70 - Interconnection Review Procedures
- Section 467.80 - Disputes
- Section 467.90 - Records
- Appendix A - Certificate of Completion
- Appendix B - Application
- Appendix C - Contract
- Appendix D - Interconnection Feasibility Study Agreement
- Appendix E - Interconnection System Impact Study Agreement
- Appendix F - Interconnection Facilities Study Agreement
Current through Register Vol. 48, No. 38, September 20, 2024
AUTHORITY: Implementing Section 16-107.5 of the Public Utilities Act [220 ILCS 5 ] and authorized by Sections 16-107.5 and 10-101 of the Public Utilities Act [220 ILCS 5 ].
Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.