Illinois Administrative Code
Title 83 - PUBLIC UTILITIES
Part 466 - ELECTRIC INTERCONNECTION OF DISTRIBUTED GENERATION FACILITIES
Section 466.50 - Interconnection Requests

Universal Citation: 83 IL Admin Code ยง 466.50

Current through Register Vol. 48, No. 12, March 22, 2024

a) Applicants seeking to interconnect a DER facility shall submit an interconnection request to the EDC that owns the electric distribution system to which interconnection is sought. Applicants shall use interconnection request forms approved by the Commission.

b) EDCs may charge a fee by level that an applicant must remit in order to process an interconnection request. The EDCs shall not charge more than the fees specified in the interconnection request application forms (Appendices A and D).

c) Interconnection requests may be submitted electronically.

Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.