Certificate of Completion

(To be completed and returned to the EDC when installation is complete

and final electric inspector approval has been obtained[1])

Interconnection Customer Information

Name: _____________________________________________________

Mailing Address: _____________________________________________

City: _________________ State: _________ Zip Code: ______________

Telephone (Daytime): ________________ (Evening): ________________

Facsimile Number: ________________ E-Mail Address: ______________

InstallerCheck if owner-installed

Name: ____________________________________________________

Mailing Address: ____________________________________________

City: __________________ State: _________ Zip Code: _____________

Telephone (Daytime): ________________ (Evening): ________________

Facsimile Number: ________________ E-Mail Address: ______________

Final Electric Inspection and Interconnection Customer Signature

The distributed generation facility is complete and has been approved by the local electric inspector having jurisdiction. A signed copy of the electric inspector's form indicating final approval is attached. The interconnection customer acknowledges that it shall not operate the distributed generation facility until receipt of the final acceptance and approval by the EDC as provided below.

Signed: ___________________________ Date: ___________________

(Signature of interconnection customer)

Printed Name: ____________________________

Check if copy of signed electric inspection form is attached

Check if copy of as built documents is attached (projects larger than 25 kW only)

..................................................................................................................

Acceptance and Final Approval for Interconnection (for EDC use only)

The interconnection agreement is approved and the distributed generation facility is approved for interconnected operation upon the signing and return of this Certificate of Completion by EDC:

Electric Distribution Company waives Witness

Test? (Initial) Yes(____)No(____)

If not waived, date of successful

Witness Test: __________ Passed: (Initial) ____________

EDC Signature: ____________________ Date: ____________________

Printed Name: _____________________ Title: ____________________

[1] Prior to interconnected operation, the interconnection customer is required to complete this form and return it to the EDC. Use contact information provided on the EDC's web page for generator interconnection to obtain mailing address/fax number/e-mail address.

Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.