Illinois Administrative Code
Title 83 - PUBLIC UTILITIES
Part 415 - UNIFORM SYSTEM OF ACCOUNTS FOR ELECTRIC UTILITIES
Subpart B - ADDITIONS TO AND DELETIONS FROM CFR PROVISIONS
Section 415.430 - Electric Plant Instruction 3

Current through Register Vol. 48, No. 38, September 20, 2024

In Electric Plant Instruction 3, "Components of Construction Cost," the changes set forth in the remainder of this Section are made.

a) In Paragraph (17)(b), the words "Federal Energy Regulatory" are added between "the" and "Commission's".

b) The following is added at the end of Paragraph (17)(b):

"If the balance for S (Short-term debt balances) exceeds the balance for W (Average balance in construction work in progress plus nuclear fuel in process of refinement, conversion, enrichment and fabrication), the maximum total AFUDC rate to be utilized will be the weighted average short-term debt rate. In instances where this occurs, the entire credit for AFUDC will be recorded in Account 432, Allowance for borrowed funds used during construction - credit."

c) The following is added as Paragraph (17)(c):

"(c) All deviations from the AFUDC formula shown in Electric Plant Instruction 3(17)(a) above must have approval from the Commission before implementation. In determining whether to approve such deviations, the Commission will consider the degree to which current securities issues have changed the embedded cost included in the annual computation provided in the formula."

Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.