Illinois Administrative Code
Title 83 - PUBLIC UTILITIES
Part 285 - STANDARD INFORMATION REQUIREMENTS FOR PUBLIC UTILITIES AND TELECOMMUNICATIONS CARRIERS IN FILING FOR AN INCREASE IN RATES
Subpart H - RATE AND TARIFF SCHEDULES
Section 285.5110 - Schedule E-6: Embedded Class Cost-of-Service Studies - Electric and Gas Utilities
Universal Citation: 83 IL Admin Code ยง 285.5110
Current through Register Vol. 48, No. 38, September 20, 2024
Each electric and gas utility with $5 million or more in total jurisdictional annual revenues shall submit, at a minimum, an embedded cost-of-service study for each rate increase application based on costs for the proposed test year. This submission shall consist of two parts:
a) Schedule E-6: A full set of cost-of-service results that presents the functionalization, classification and allocation to the utility's rate classes of all Illinois jurisdiction costs on the utility system as follows:
1) All costs broken down by ICC Account or
group of similar ICC Accounts that are allocated on the same basis;
2) Test year costs shall be consistent with the
costs presented in Section
285.3005.
3) A list of all externally generated allocation
factors in the study;
4) Rates-of-return
by customer classes under both present and proposed rates; and
5) A full narrative description of the allocation
methodology used in the cost-of-service study that explains in detail:
A) The derivation of all externally generated
allocators; and
B) The basis for all
direct assignments of costs in the study.
b) Schedule E-6 work papers: the utility shall provide all materials relied on in developing the cost-of-service study. This shall include:
1) All work papers relied on to develop
the cost-of-service study;
2) The
following data on demand and/or energy loss factors used in the cost-of-service
study:
A) A list of all demand and/or energy loss
factors by customer class used in the study; and
B) All studies or analyses relied on to develop
these loss factors;
3) All
other studies and analyses relied on by the utility to develop cost-of-service study
results; and
4) A working model of the
utility's cost-of-service study. If the utility is prevented from fulfilling this
requirement by an agreement with an outside vendor, provide the following:
A) The contract provisions that prevent the
utility from distributing a working "unprotected" version of the study;
and
B) Either allow intervenors access
to a computer that contains a working "protected" version of the model, i.e.,
formulas may be hidden to prevent viewing, where they can generate alternative
cost-of-service study results; or have the utility's vendor and individual
intervenors enter into an agreement to provide the intervenors with a working
"unprotected" version of the model to use for a fixed and limited time period at the
end of which that right to use the program would expire.
Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.