Each electric and gas utility with $5 million or more in total jurisdictional annual revenues shall submit, at a minimum, an embedded cost-of-service study for each rate increase application based on costs for the proposed test year. This submission shall consist of two parts:

a) Schedule E-6: A full set of cost-of-service results that presents the functionalization, classification and allocation to the utility's rate classes of all Illinois jurisdiction costs on the utility system as follows:

1) All costs broken down by ICC Account or group of similar ICC Accounts that are allocated on the same basis;

2) Test year costs shall be consistent with the costs presented in Section 285.3005.

3) A list of all externally generated allocation factors in the study;

4) Rates-of-return by customer classes under both present and proposed rates; and

5) A full narrative description of the allocation methodology used in the cost-of-service study that explains in detail:
A) The derivation of all externally generated allocators; and

B) The basis for all direct assignments of costs in the study.

b) Schedule E-6 work papers: the utility shall provide all materials relied on in developing the cost-of-service study. This shall include:

1) All work papers relied on to develop the cost-of-service study;

2) The following data on demand and/or energy loss factors used in the cost-of-service study:
A) A list of all demand and/or energy loss factors by customer class used in the study; and

B) All studies or analyses relied on to develop these loss factors;

3) All other studies and analyses relied on by the utility to develop cost-of-service study results; and

4) A working model of the utility's cost-of-service study. If the utility is prevented from fulfilling this requirement by an agreement with an outside vendor, provide the following:
A) The contract provisions that prevent the utility from distributing a working "unprotected" version of the study; and

B) Either allow intervenors access to a computer that contains a working "protected" version of the model, i.e., formulas may be hidden to prevent viewing, where they can generate alternative cost-of-service study results; or have the utility's vendor and individual intervenors enter into an agreement to provide the intervenors with a working "unprotected" version of the model to use for a fixed and limited time period at the end of which that right to use the program would expire.

Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.