Illinois Administrative Code
Title 83 - PUBLIC UTILITIES
Part 285 - STANDARD INFORMATION REQUIREMENTS FOR PUBLIC UTILITIES AND TELECOMMUNICATIONS CARRIERS IN FILING FOR AN INCREASE IN RATES
Subpart E - RATE BASE SCHEDULES
Section 285.2060 - Schedule B-7.1: Construction Work in Progress Percent Complete

Current through Register Vol. 48, No. 38, September 20, 2024

a) For the projects identified in Schedule B-7, provide information to determine the estimated percent complete, or for a future test year, expected to be complete, at the end of the test year.

b) Information provided shall include:

1) Project number;

2) Description of project;

3) Date project started;

4) Most recent estimated project completion date;

5) Original budget estimate;

6) Most recent revised estimate;

7) Accumulated construction costs; and

8) Percent complete (the amount in subsection (b)(7) divided by the amount in subsection (b)(6) x 100).

Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.