a) Provide information required by subsection (b) for each construction project included in Construction Work in Progress (CWIP) for the test year rate base that exceeds 5% of the total CWIP balance for the test year. If the CWIP project is not in rate base, the information is not required.

b) Information provided shall include:

1) Project number;

2) Description of project;

3) Direct costs of construction through the end of the test year;

4) Allowance for funds used during construction (AFUDC) or interest during construction (IDC) for telecommunications carriers capitalized through the end of the test year;

5) Other indirect costs through the end of the test year;

6) Total cost of construction project through the end of the test year; and

7) Amount included in the test year jurisdictional rate base.

Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.