Illinois Administrative Code
Title 8 - AGRICULTURE AND ANIMALS
Part 900 - LIVESTOCK MANAGEMENT FACILITY REGULATIONS
Subpart E - LIVESTOCK WASTE HANDLING FACILITIES OTHER THAN LAGOONS
Section 900.504 - Livestock Waste Handling Facilities Subject to the Public Informational Meeting Process
Current through Register Vol. 48, No. 12, March 22, 2024
For a livestock waste handling facility, other than a livestock waste lagoon, that is subject to the public informational meeting process as outlined in Section 12 of the Livestock Management Facilities Act [510 ILCS 77 ] and Subpart D of this Part, the following procedures shall be followed:
a) The owner or operator shall file a completed registration with the Department, on a form provided by the Department, at least 37 calendar days prior to the anticipated dates of construction.
b) The registration shall include the following:
c) The Department shall, within 15 calendar days after receipt of the registration form, notify the person submitting the form that the registration is complete or that clarification information is needed. [510 ILCS 77/11(c) ] No later than 15 calendar days after receipt of the clarification information, the Department shall notify the owner or operator that registration is complete or that additional clarification is needed.
d) When the county board requests an informational meeting, construction shall not begin until after the informational meeting has been held, the Department has reviewed the county board's recommendation and replied to the recommendation indicating if the proposed new livestock management facility or the new livestock waste handling facility is or will be in compliance with the requirements of the Act, and the owner, operator, or certified manager and operator has received the Department's notice that the setbacks and all applicable requirements of the Act have been met. [510 ILCS 77/12(c) ] If no informational meeting is held, the Department shall, within 15 calendar days following the end of the period for the county board to request an informational meeting, notify the owner or operator that construction may begin or that clarification is needed. [510 ILCS 77/12.1(b) ]