This Section provides for the issuance of a Notice of Closure following the satisfactory completion of corrective actions and submittal of a corrective action report.
a) Upon completion of the activities described in the approved corrective action plan, the owner or operator shall submit a corrective action report to the Department. The report must provide adequate evidence to demonstrate that the actions were completed in accordance with the approved plan and that the cleanup objectives have been attained.
b) The corrective action report shall provide the following:
1) certification, by the
facility owner and by the licensed professional geologist, professional
engineer or licensed industrial hygienist who conducted the site assessments
and supervised implementation of the corrective action plan, that all
components of the approved corrective action plan were fully
implemented;
2) facility site maps,
at a scale no larger than 1 inch equal to 200 feet, of sufficient detail and
accuracy to show all of the following:
A) the
boundaries of the facility;
B) any
areas of the site from which agrichemical contaminated soils were
removed;
C) any areas of the site
on which an engineered barrier was installed; and
D) the map scale (graphic and nominal), north
arrow, date, name and address of preparer, and location of the site with
respect to section, township, range, and principal meridian;
3) a list of the agrichemicals
that were included in the soil or groundwater remediation activities;
4) documentation of the volume of soil
removed from the site and how the contaminated soil was disposed of;
5) as-built drawings of any engineered
barriers constructed to achieve the approved remediation objectives;
6) copies of any documents describing
institutional controls accompanying engineered barriers;
7) if groundwater remediation activities were
conducted, copies of all analytical results of groundwater monitoring to
demonstrate that the approved groundwater cleanup objectives were attained;
and
8) the results of a final
inspection by representatives of the Department or Board.
Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.