Section 1130.770 - Project Completion, Final Realized Costs and Cost Overruns
Current through Register Vol. 48, No. 12, March 22, 2024
a) Written Notification
b) For projects with no cost, the permit holder shall submit a written notice to HFSRB of the project's conclusion (e.g., initiation of a new service, discontinuation, certification of additional dialysis stations).
c) For a project with a cost below the capital expenditure minimum, the permit holder shall submit a notice that the project has been brought to a conclusion and submit a report of final realized costs containing the following:
d) For a project with a cost above the capital expenditure minimum in place at the time of permit approval, the permit holder shall submit a notice that the project has been brought to a conclusion and submit a report of final realized costs containing the following:
e) Failure to file final realized costs reports will result in subsequent applications for permit filed by the permit holder to be deemed incomplete by HFSRB staff until the required report is filed. In addition, the permit holder will be subject to fines, penalties and sanctions as mandated in the Act (see 20 ILCS 3960/14.1 ) and Section 1130.790.
f) Failure to timely file the project's report of project completion and final realized costs, all necessary supporting documentation following the project completion, or any project cost overrun information shall subject the permit or exemption holder to fines, permit revocation, and the penalties and sanctions mandated in the Act (see 20 ILCS 3960/14.1) and Section 1130.790.
g) Any amount of the final realized cost that exceeds the approval permit amount shall be considered a cost overrun without a permit unless the amount is subsequently approved by HFSRB. Projects may deviate from the costs, fees, and expenses provided in their project cost information for the project's cost components, provided that the final total project cost does not exceed the approved permit amount [20 ILCS 3960/5 ].
h) Any project with a cost overrun shall not be complete until HFSRB determines that the project has complied with all project completion requirements, as determined by HFSRB.
i) Any project that is compliant with the conditions of its permit shall not be complete until HFSRB determines that the project completion requirements have been met.