Written protests or objections regarding a procurement action or decision must be received by the Director of Purchasing at his/her office within seven calendar days of the award of the contract.

Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.