Illinois Administrative Code
Title 62 - MINING
Part 245 - HYDRAULIC FRACTURING REGULATORY ACT
Subpart H - HIGH VOLUME HORIZONTAL HYDRAULIC FRACTURING PREPARATIONS AND OPERATIONS
Section 245.820 - Secondary Containment Inspections

Current through Register Vol. 48, No. 12, March 22, 2024

No more than one hour before initiating any stage of the high volume horizontal hydraulic fracturing operations, all secondary containment required pursuant to Section 245.825(b) must be visually inspected by the permittee or the contractor performing the HVHHF operations on behalf of the permittee to ensure that all structures and equipment are in place and in proper working order. The results of this inspection must be recorded and documented by the permittee or the contractor performing the HVHHF operations on behalf of the permittee on a form prescribed by the Department, maintained in the well file, and made available at the well site to the Department upon request. (Section 1-75(c)(13) of the Act)

Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.