Illinois Administrative Code
Title 62 - MINING
Part 1784 - UNDERGROUND MINING PERMIT APPLICATIONS - MINIMUM REQUIREMENTS FOR RECLAMATION AND OPERATION PLAN
Section 1784.23 - Operation Plan: Maps and Plans
Current through Register Vol. 48, No. 12, March 22, 2024
Each application shall contain maps, plans, and cross-sections of the proposed permit and adjacent areas as follows:
a) The maps, plans and cross-sections shall show the underground mining activities to be conducted, the lands to be affected throughout the operations, and any change in a facility or feature to be caused by the proposed operations, if the facility or feature was shown under 62 Ill. Adm. Code 1783.24 and 1783.25;
b) The following shall be shown for the proposed permit area:
c) Except as provided in Sections 1784.16(a)(2), 1784.16(a)(3), 1784.19, and 62 Ill. Adm. Code 1817.71(b), 1817.74(c) and 1817.81(c), cross-sections, maps and plans required under subsections (b)(4), (5), (6), (10) and (11) shall be prepared by, or under the direction of, and sealed by a qualified registered professional engineer licensed under The Illinois Professional Engineering Act (Ill. Rev. Stat. 1985, ch. 111, pars. 5101-5137), a qualified registered structural engineer licensed under The Illinois Structural Engineering Act (Ill. Rev. Stat. 1985, ch. 111, pars. 6501-6530), or a qualified registered professional land surveyor licensed under The Illinois Land Surveyors Act (Ill. Rev. Stat. 1985, ch. 111, pars. 3201-3234), with assistance from experts in related fields such as geology and landscape architecture.