Each application shall contain maps and plans as follows:
a) The maps and plans shall show the lands proposed to be affected throughout the operations and any change in a facility or feature to be caused by the proposed operations, if the facility or feature was shown under 62 Ill. Adm. Code 1779.24 through 1779.25.
b) The following shall be shown for the proposed permit area unless also specifically required for the adjacent area by the requirements of this Section:
c) Except as provided in Section 1780.25(a)(2), 1780.25(a)(3), 1780.35(a), and 62 Ill. Adm. Code 1816.71(b), 1816.74(c) and 1816.81(c), cross-sections, maps and plans required under subsections (b)(4), (5), (6), (10) and (11) shall be prepared by, or under the direction of, and sealed by a qualified registered professional engineer licensed under The Illinois Professional Engineering Act (Ill. Rev. Stat. 1985, ch. 111, pars. 5101-5137), a qualified registered structural engineer licensed under The Illinois Structural Engineering Act (Ill. Rev. Stat. 1985, ch. 111, pars. 6501-6530), or, if authorized by state law, a qualified registered professional land surveyor licensed under The Illinois Land Surveyors Act (Ill. Rev. Stat. 1985, ch. 111, pars. 3201-3234), with assistance from experts in related fields such as geology and landscape architecture.