Illinois Administrative Code
Title 44 - GOVERNMENT CONTRACTS, GRANTMAKING, PROCUREMENT AND PROPERTY MANAGEMENT
Part 990 - PREQUALIFICATION OF CONSTRUCTION MANAGERS
Subpart B - SUSPENSION, DEBARMENT, MODIFICATION OF PREQUALIFICATION, AND CONDITIONAL PREQUALIFICATION
Section 990.300 - Actions Affecting Responsibility and Prequalification
Current through Register Vol. 48, No. 38, September 20, 2024
At any time, CDB may consider whether an action is warranted concerning a CM's prequalification. Actions that may be taken include one or more of the following:
a) Interim or Emergency Suspension or Modification
CDB may summarily suspend or modify a CM's prequalification in accordance with Section 16 of the Capital Development Board Act [20 ILCS 3105/16] .
b) Debarment
CDB may debar a CM to exclude it from making submittals for CDB contracts as authorized by statute. The period of debarment shall be not less than five years and may be permanent when warranted or as authorized by law [20 ILCS 3105/16] .
c) Modification of Prequalification
CDB may modify or restrict a CM's prequalification as appropriate, including, but not limited to, one or more of the following:
d) Conditional Prequalification
CDB may condition prequalification (which may be otherwise limited) on the CM's successful utilization of a management plan, evaluations, conferences, or other methods designed to achieve satisfactory performance or compliance with contract requirements.
e) Suspension
CDB may suspend a CM firm or disqualify a CM firm temporarily from submitting for a CDB contract, for a period of time up to five years. The CM's failure to timely pursue administrative action as provided by Subpart D of this Part shall constitute consent of the CM to CDB's action.