Illinois Administrative Code
Title 44 - GOVERNMENT CONTRACTS, GRANTMAKING, PROCUREMENT AND PROPERTY MANAGEMENT
Part 990 - PREQUALIFICATION OF CONSTRUCTION MANAGERS
Subpart A - RESPONSIBILITY
Section 990.200 - Processing of Construction Manager Prequalification Application
Current through Register Vol. 48, No. 38, September 20, 2024
a) CMs must complete a prequalification application, including the Financial Interests and Potential Conflicts of Interest forms required under Section 50-35 of the Illinois Procurement Code [30 ILCS 500/50-35] .
b) Applications for renewal will ordinarily
be sent to the CMs approximately 60 days before the expiration of current
prequalification and are available electronically on CDB's Internet site at
c) Processing of applications (either initial or renewal) by CDB will require up to 45 days after receipt of all requested information and a completed application. When any information is incomplete or unsatisfactory, a longer processing time will be required. CMs will be notified when information is incomplete or unsatisfactory.
d) Unless otherwise specified in writing by CDB, the term of prequalification shall be two years from the end of the month the prequalification begins. When prequalification is granted, the CM will be notified in writing of the expiration date, which will also be entered on CDB's electronic program. CDB may grant a shorter term of prequalification by agreement with the CM, when a determination is made that a shorter period is justified, or when a special prequalification is developed specifically for a certain project. Updated or new CM information including the term of prequalification will be entered on CDB's electronic program weekly. At the beginning of each month, a list of CMs whose prequalification expires in approximately 60 days will be generated.
e) Applications may be sent to CDB by facsimile or e-mail.
f) CDB shall review and evaluate each application received, which may include one or more of the following actions:
g) The criteria to be evaluated include whether the CM has adequate resources.
h) CDB shall grant prequalification to those applicants who:
i) The fact that an applicant may be prequalified does not necessarily represent a finding of responsibility for a particular procurement.
j) CDB shall deny prequalification to any firm that has not affirmatively demonstrated its responsibility.
k) CDB's determination of responsibility shall be final.