Illinois Administrative Code
Title 44 - GOVERNMENT CONTRACTS, GRANTMAKING, PROCUREMENT AND PROPERTY MANAGEMENT
Part 8 - CHIEF PROCUREMENT OFFICER FOR THE CAPITAL DEVELOPMENT BOARD
Subpart N - SELECTION OF CONSTRUCTION-RELATED PROFESSIONAL SERVICES, CONSTRUCTION MANAGEMENT SERVICES AND DESIGN-BUILD ENTITIES
Section 8.3105 - Phase 2 Design-Build Evaluation
Current through Register Vol. 48, No. 38, September 20, 2024
a) In Phase 2, CDB will evaluate and rank the selected DB entities based on their technical and cost proposals.
b) Evaluation shall be based on the technical and cost submission components and relative importance or weighting of the technical and cost submission components as set forth in the RFP.
c) Proposals shall not be reviewed until after the deadline for submission has passed.
d) Proposals must meet all material requirements of the RFP or they may be rejected as non-responsive.
e) CDB shall have the right to reject any and all proposals subject to approval by the CPO.
f) CDB shall maintain a record of the evaluation scoring to be disclosed in event of a protest.
g) CDB shall include the following criteria in the Phase 2 technical evaluation of DB entities:
h) CDB shall include the following criteria in every Phase 2 cost evaluation:
i) CDB shall directly employ or retain a licensed design professional to evaluate the technical and cost submissions to determine if the technical submissions are in accordance with generally accepted industry standards.