Prior to a State agency issuing an award, the State agency must verify that there are no outstanding pre-award requirements. This includes verification of qualification, acceptance of risk assessments, approved budget, conflict of interest disclosures, and required certifications. All outstanding pre-award requirements must be resolved before a NOSA can be issued. This verification is automated either through the statewide grant management system or through the CSFA.
a) If there are no outstanding requirements, the State awarding agency must issue a NOSA through the CSFA to comply with federal requirements.
b) The NOSA shall communicate:
c) The State awarding agency shall release the NOSA to the applicant from the CSFA. The applicant shall receive the NOSA through the Grantee Portal.
d) The applicant shall review the NOSA and determine whether it will accept the specified terms of the award.
e) Upon applicant acceptance of the NOSA, the State awarding agency shall initiate the Grant Agreement following the State agency's protocol.