Illinois Administrative Code
Title 44 - GOVERNMENT CONTRACTS, GRANTMAKING, PROCUREMENT AND PROPERTY MANAGEMENT
Part 6 - CHIEF PROCUREMENT OFFICER FOR THE DEPARTMENT OF TRANSPORTATION - CONTRACT PROCUREMENT
Subpart M - PROCUREMENT OF SERVICES UNDER CONSTRUCTION MANAGER/GENERAL CONTRACTOR PROJECT, PROGRESSIVE DESIGN-BUILD, AND DESIGN-BUILD DELIVERY METHODS
Section 6.1070 - Project Labor Agreement

Universal Citation: 44 IL Admin Code ยง 6.1070
Current through Register Vol. 48, No. 38, September 20, 2024

A CMGC contract, DB contract, or PDB contract shall require the design-build contractor, progressive design-build contractor or CMGC contractor to enter into a project labor agreement used by the Department unless the transportation project is federally funded and the application of those requirements would jeopardize the receipt or use of federal funds in support of the transportation project as determined by the Department. This requirement does not apply to construction-related professional services.

Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.