Section 6.385 - Expenditure in Excess of Contract Price
Current through Register Vol. 48, No. 38, September 20, 2024
a) No funds in excess of the contract price may be obligated or expended by change order or contract adjustment unless the additional work to be performed or materials to be furnished are germane to the original contract.
b) A construction contract change order may cause the obligation or expenditure of funds in excess of the original contract amount provided the subject of the change order is germane to the original contract and the Department determines the additional expenditure is approved in accordance with Section 30-35 of the Code. The Department will approve construction contract change orders without supplemental procurement procedures in accordance with the following requirements and thresholds.
c) A construction contract adjustment is germane to the original contract. If a contract adjustment requires additional obligation or expenditure in excess of $100,000, the Department will record the provisions of the original contract in the contract payment file as authority for the addition.
d) Contract change orders and contract adjustments will be processed on a form prescribed by the Department.