a) Inspection of Plant or Site
The CPO-HE or a designee may enter a vendor's or subcontractor's plant or place of business and, pursuant to contract provisions, if any:
b) The presence or absence of an inspector shall not relieve the vendor or subcontractor from any requirements of the contract.
c) When an inspection is made in the plant or place of business of a vendor or subcontractor, the vendor or subcontractor shall provide without charge all reasonable facilities and assistance for the safety and convenience of the person performing the inspection or testing.
d) Inspection or testing of supplies and services performed at the plant or place of business of any vendor or subcontractor shall be performed so as not to unreasonably delay the work of the vendor or subcontractor.
e) On-site inspection of construction shall be performed, in accordance with the terms of the contract, provided that the CPO-HE's, SPO's or PCM's activities shall not be unduly restricted by any such contract provision.