a) Inspection of Plant or Site
The IOC may enter a contractor's or subcontractor's plant or place of business to:
1) inspect
supplies or services for acceptance by the State pursuant to the terms of a
contract;
2) audit the books and
records of any contractor or subcontractor pursuant to Section
1120.7020;
3) investigate an action to debar or suspend
a person from consideration for award of contracts pursuant to the
Code;
4) determine whether the
standards of responsibility have been met or are capable of being
met;
5) determine if the contract
is being performed in accordance with its terms; and
6) accomplish any other purpose permitted by
law.
b) Inspection and Testing of Supplies and Services
1)
Solicitation and Contractual Provisions. State contracts may provide that the
IOC may inspect supplies and services at the contractor's or subcontractor's
facility and perform tests to determine whether they conform to solicitation
requirements, or, after award, to contract requirements, and are therefore
acceptable. Inspections and tests shall be conducted in accordance with the
terms of the solicitation and contract.
2) Procedures for Trial Use and Testing. The
CPO may establish operational procedures governing the testing and trial use of
equipment, material and other supplies, and the application of resulting
information and data to specifications or procurements.
c) Conduct of Inspections
1) Inspectors. Inspections or tests shall be
performed so as not to unduly delay the work of the contractor or
subcontractor. No inspector may change any provision of the specifications or
the contract without the written authorization of the CPO. The presence or
absence of an inspector shall not relieve the contractor or subcontractor from
any requirements of the contract.
2) Location. When an inspection is made in
the plant or place of business of a contractor or subcontractor, the contractor
or subcontractor shall provide without charge all reasonable facilities and
assistance for the safety and convenience of the person performing the
inspection or testing.
3) Time.
Inspection or testing of supplies and services performed at the plant or place
of business of any contractor or subcontractor shall be performed at reasonable
times.
Disclaimer: These regulations may not be the most recent version. Illinois may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.