Section 1030.190 - Phase 2 Evaluation
Current through Register Vol. 48, No. 38, September 20, 2024
a) In Phase 2, CDB will evaluate and rank the selected DB entities based on their technical and cost proposals.
b) Evaluation shall be based on the technical and cost submission components and relative importance or weighting of the technical and cost submission components as set forth in the RFP.
c) Proposals shall not be reviewed until after the deadline for submission has passed.
d) Proposals must meet all material requirements of the RFP or they may be rejected as non-responsive.
e) CDB shall have the right to reject any and all proposals.
f) CDB shall maintain a record of the evaluation scoring to be disclosed in event of a protest regarding the solicitation.
g) CDB shall include the following criteria in the Phase 2 technical evaluation of DB entities:
h) CDB shall include the following criteria in every Phase 2 cost evaluation:
i) CDB shall directly employ or retain a licensed design professional to evaluate the technical and cost submissions to determine if the technical submissions are in accordance with generally accepted industry standards.