Illinois Administrative Code
Title 44 - GOVERNMENT CONTRACTS, GRANTMAKING, PROCUREMENT AND PROPERTY MANAGEMENT
Part 1025 - SELECTION OF CONSTRUCTION MANAGERS
Section 1025.140 - Evaluation Procedures
Current through Register Vol. 48, No. 12, March 22, 2024
a) In making its recommendations, the selection committee may consider, among other items:
b) Before beginning review of the CM's statements of qualifications, the committee shall prepare a table of the factors the CMs will be rated on and the weight to be assigned to each factor. The table of factors, and the scores of each reviewed submittal, will be kept on file for no less than two years from the date of the selection.
c) In no case shall the committee, prior to selecting a CM for negotiation, seek formal or informal submission of verbal or written estimates of costs or proposals in terms of dollars, hours required, percentage of construction cost, or any other measure of compensation.